Columbia Hills Construction Schedule July – August 2016

COLUMBIA HILLS PROJECT
6 WEEK LOOK AHEAD SCHEDULE
Below is a summary of activities occurring within the next six (6) weeks:
Week of June 27:
• Install super silt fencing and silt fencing along remainder of property line.
• Demolition of storage shed and lot pavement.
Week of July 5:
• Installation of underpinning at Columbia Grove Building 1024.
• Install new curbs & gutters around playground.
• Install main construction entrance.
• Install Phase 2B temporary fencing.
Week of July 11:
• Installation of underpinning at Columbia Grove Buildings
• Installation of new dumpster pad.
• Demolition and grading of existing playground areas.
Week of July 18:
• Installation of underpinning at Columbia Grove Buildings
• Pave new parking lots.
Week of July 25:
• Start site grading
• Start pile installation for pile wall and retaining walls
• Pave new parking lots
Week of August of August 1:
• Move into Phase 2C if lots are not utilized
• Continue with pile operations and grading.
For further information, please contact Bozzuto Construction (BCC) Superintendent.
BCC Superintendent Contact Information: Colin Courtillet Mobile: 202-437-0322