Columbia Hills Construction Schedule June – July 2016

COLUMBIA HILLS PROJECT

Below is a summary of activities occurring within the next six weeks:

 

Week of June 13:

– Installation of temporary fencing to start removal of trees.

– Removal of existing trees at west side of project, adjacent to Carlyle House.

– Root pruning of existing trees at west side of project, adjacent to Carlyle House.

– Install super silt fencing and silt fencing along north property line.

– Demolition of existing storage shed.

– Earthwork and miscellaneous demolition of parking lot.

 

Week of June 20:

– Removal of existing trees at West side of project, adjacent to Carlyle House.

 -Root pruning of existing trees at West side of project, adjacent to Carlyle House.

– Install tree protection fencing along north property line.

– Earthwork and miscellaneous demolition of parking lot.

 

Week of June 27:

– Removal of existing trees at West side of project, adjacent to Carlyle House.

– Root pruning of existing trees at West side of project, adjacent to Carlyle House.

– Install tree protection fencing along north property line.

– Install super silt fencing and silt fencing along remainder of property line.

– Install storm water structures adjacent to new playground.

 

Week of July 5:

– Installation of underpinning at Columbia Grove Building 1024

– Install new curbs & gutters around playground

– Construct new segmental retaining wall

 

Week of July 11:

– Installation of underpinning at Columbia Grove Building 1018

– Installation of underpinning at Columbia Grove Building 1012

 

Week of July 18:

– Installation of underpinning at Columbia Grove Building 1012

– Install new dumpster pad near playground

 

For further information, please contact Bozzuto Construction (BCC) Superintendent.